The details of the two BOT project is as under.
1) Construction of Sangamner Loni Kolhar Road (S.H.44) Km.No.89/300 to 118/000 and (S.H.45) Km. No. 41/200 to 48/700 (36.800 Kms.)
The project involved construction of 36/800 Kms road between Sangamner Loni Kolhar Ahmednager Dist. M.S.
The Toll Collection started in March 2006 and the concession period is up to year 2022.
2) Reconstruction / Widening of 18 Narrow & Weak Bridges on Badnera – Yeotmal – Wani – Ghuggus Road (M.S.H.No. 6) Under BOT Basis.
The work involved Construction Reconstruction / Widening of 18 Narrow & Weak Bridges on Bednera – Yeotmal – Wani – Ghuggus Road Yeotmal Dist Maharashtra.
The Toll Collection started in August 2002 . The Concession period is up to August 2010.